A work is done by the people in 24 min. one of them can do this work a lonely in 40 min.How much time required to do the same work for the second person

Choose the correct answer:
A) 30 min
B) 60 min
C) 45 min
D) Data Insufficient
Detailed Explanation

No Explanation